Club Stand Build Diary July 2018

The wait is almost over. 

The Final Club Stand Build Diary

There is a buzz around the VRC at the moment with only 19 days until practical completion of The Club Stand. Multiplex have had possession of The Club Stand site for now 604 days, not that the construction team has been counting! 

The internal of the building is starting to look like a work of art, with the details of the build and the images we have all looked at for a long time now turning into reality. 

Witness Testing has continued with all consultants, architects and VRC facilities being happy with the result. The MFB (Metropolitan Fire Brigade) completed its inspection on Monday which is an important step in ensuring that the final Occupancy Permit for the building can be issued. Works have accelerated in the Members Betting Ring with the totes, bookmakers and turnstile structures well underway. 

Works to be completed over the next fortnight:

Ground Floor
Commence client & architectural defects 
Lounge stone installation 
Grand stair handrail installation 
Grand stair balustrade completion 
Grand stair void carpet install 

Level 1
Continue architect inspections in The Champagne Bar & The Members Bar 

Level 2
Furlong Bar completion 
Dining Room completion 
Commissioning & final clean of kitchens 

Level 3
Final finishes in The Byerley, architect inspections occurring 
Straight Six – Gateway display & host desk completion 

Level 4
Lay permanent carpet in internal venue 
Complete paving & external decking to exterior 

External
Patching to external soffit on north west 
Painting to external soffit on north east 
Continue patching & painting around perimeter 
Permanent handrail install to all seating areas 

Roof
Fabric feature roof continuation 