Club Stand Build Diary. New Members Grandstand at Flemington Racecourse.

Club Stand Build Diary

The fit out within the Club Stand has continued to provide excellent progress over the past week. The main activities are now seeing the fit out of all venues coming close to the finished product – what an exciting time it is! Carpet has continued to be installed, with Levels 1-3 now fully finished on the floors, with the timber floor in the Straight Six currently being laid.

Works have also progressed well in the external areas with external seating coming to a conclusion. The Betting Ring structures which will cater for turnstiles, totes and bookmakers currently being installed. Multiplex has also removed some of the hoarding to allow ground works in the external areas to continue. There is so much happening on the site that it is impossible to mention it all! Multiplex is doing a fantastic job managing all the finishing trades, with the mood on site being a collaborative and happy workforce as the finish line is in sight.

Works to be completed over the next fortnight:

WEEK 76:

4/6/18 – 10/6/18

Roof

Continue membrane roof works

 

Level 4

Complete wall sheeting

Complete plant room fit off

Continue Facade install

Commence ceiling installation

 

Level 3

Complete ceiling framing and sheeting

Continue bar/kitchen tiling

Continue kitchen/bar and joinery install

Continue kitchen/bar install

 

Level 2

Complete ceiling framing and sheeting

Continue kitchen/bar install

Continue grand stair void balustrade install

Continue kitchen/bar and joinery install

Continue carpet installation

 

Level 1

Continue champagne bar joinery install

Continue install of pods in the champagne bar

Complete installation of wall paneling

Continue installation of feature lights

 

Ground Floor

Continue ceiling framing & sheeting

Continue main stair works

Continue wall & floor tiling

Continue kitchen/bar and joinery

Continue laying external pavers

 

WEEK 77:

11/6/18 – 17/6/18

Roof

Continue membrane roof works

 

Level 4

Continue Facade install

Continue bar/kitchen tiling

Continue ceiling installation

 

Level 3

Continue bar and kitchen tiling

Continue kitchen/bar install

Continue joinery install

 

Level 2

Continue kitchen/bar install

Continue kitchen/bar and joinery install

Continue grand stair void balustrade install

Continue carpet installation

 

Level 1

Continue bar install

Continue Joinery install in champagne bar

Complete wall & floor tiling

Continue Painting

Continue installing champagne bar pods

 

Ground Floor

Continue ceiling framing & sheeting

Continue main stair works

Continue wall & floor tiling

Complete kitchen/bar and joinery install

Complete external planter boxes