Club Stand December 2017

Club Stand Diary

It has been an amazing 12 month period for the Club Stand with vast progress from year to date.  All staff should be proud of what has been achieved and how everyone has worked well to allow the process to be as smooth as possible over the 2017 calendar year. Milestones continues to occur every week on this project, with this week’s milestone being the completion of the installation of the pre-cast petals which architecturally give the building its beautiful form. 2018 is going to be bigger and better as the VRC departments continue to work together to bring this wonderful structure to the world. This is a very exciting time for all of us!


The two photos below really do tell a story of the progress that has been achieved in 2017.

Club Stand December 2017

Club Stand December 2016

COMPLETED PRE CHRISTMAS BREAK:

Roof

Ongoing roof steel installation

Precast lids installed on West core

Level 4

Slab pours completed

All precast petals installed

Level 3

Stud wall installation commenced

Commencement service rough in

Level 2

Stud wall installation

Services rough in continuation

Continuation of Façade installation

Level 1

Plaster sheeting commenced

Ongoing rough in of all services

Ground Floor

Block work installation completed

Plaster sheeting commenced

Ongoing rough in of all services

Owners and Trainers

Link bridge steel installed