VRC Club Stand as at 6 December 2017

Club Stand Build Diary

Club Stand works have continued however the weekend rain did slow progress. The demolition of the outer Betting Ring has been completed which will allow the hoarding to be moved further back to allow the works on the new Members’ Betting Ring to continue.

This week will see the concrete pour on Level 4 (rooftop). All 8 escalators for the Stand have been delivered to site and will be craned into position later this week. The installation of glass has continued on Level 1 and looks mighty impressive. Once completed the façade will provide uninterrupted views from the Club Stand of the entire Flemington site, a vantage point that did not previously exists due to the configuration of the Members Old Grandstand.

As Multiplex ramp up their program, we are now seeing approximately 130-150 personnel on site each day. Fit out works are starting to show the internal shapes of the building, especially on Ground Level and Level 1.

WEEK 53 & WEEK 54 DECEMBER 2017

The following works will be completed over the next fortnight:

WEEK 53:

4/12/17 – 10/12/17

Roof

  • Commence Roof steel installation

Level 4

  • Complete Column & beam erection
  • Continue Bondek installation
  • Continue reo installation and slab pours

Level 3

  • Complete concourse reo and slabs
  • Commence Fire spray
  • Commence Service rough in

Level 2

  • Complete concourse reo and slabs
  • Complete Fire spray
  • Continue Service rough in
  • Continue façade bracket installation
  • Commence wall set out and stud installation

Level 1

  • Complete Fire spray
  • Complete façade bracket installation
  • Continue Service rough in
  • Continue wall set out and stud installation
  • Continue façade installation
  • Commence balustrade installation

Ground Floor

  • Continue services rough in
  • Continue plant room fit out
  • Commence stud installation

WEEK 54:

11/12/17 – 17/12/17

Roof

  • Continue roof steel installation
  • Install pre-cast lids to cores

Level 4

  • Complete Bondek, continue slab

Level 3

  • Complete Fire spray
  • Continue Service rough in
  • Commence façade bracket installation
  • Commence wall set out and stud installation

Level 2

  • Continue Service rough in

  • Continue wall installation
  • Commence façade installation
  • Commence balustrade installation

Level 1

  • Continue Service rough in
  • Continue wall set out and stud installation
  • Continue façade installation
  • Continue block work
  • Continue balustrade installation
  • Commence plasterboard installation

Ground Floor

  • Continue Service rough in
  • Continue Plantroom fit out
  • Commence plasterboard installation