Club Stand Build Diary

Multiplex returned to Flemington on Tuesday 14th November after taking a break over the Melbourne Cup Carnival. Works will now see the further installation of steel and concrete to Level 3 and Rooftop, which will be completed prior to the Christmas Break. The rough in of services has commenced on ground level, and will continue up the building.

WEEK 51:

20/11/17 – 26/11/17

Level 4

  • Continue Column & beam steel erection

  • Continue bondek installation

  • Commence reo installation

Level 3

  • Continue column and beam steel erection

  • Continue reo installation and slab pours

Level 2

  • Commence fire spraying

  • Continue services rough in

  • Commence concourse reo and slab preparation

Level 1

  • Continue Fire spray and services rough in

  • Continue façade bracket installation

  • Commence wall set out and stud installation

Ground Floor

  • Continued services rough in

  • Continue plant room fit out

  • Continue blockwork installation

  • Commence wall set out and stud installation

WEEK 52:

27/11/17 – 3/12/17

Level 4

  • Continue Column & beam steel erection

  • Continue bondek installation

  • Commence slab pours

Level 3

  • Continue column and beam steel erection

  • Continue reo installation and slab pours

Level 2

  • Continue fire spray

  • Continue services rough in

  • Continue concourse reo and slab preparation

  • Commence façade bracket installation

Level 1

  • Continue fire spray and services rough in

  • Continue façade bracket installation

  • Continue thermal installation

  • Continue wall set out and stud installation

Ground Floor

  • Plant room fit-out ongoing

  • Continue services rough in