Photograph of the construction area for the new Club Stand at Flemington.

Club Stand Build Diary

The following work will be completed over the next fortnight:

Week Commencing Monday 3 July

  • Complete blinding to east tunnel
  • Strip formwork from east core
  • Continue Installation of precast concrete to Western Basement tunnel
  • Installation of crane starter legs

Week commencing Monday 10 July

  • Back filling of precast wall to Owners and Trainers Stand and Basement Tunnel
  • Commence Installation of precast concrete to Eastern Basement Tunnel
  • Continuation of storm water pipe and pit installation