Photograph of the construction zone of the new Club Stand at Flemington Racecourse.

Club Stand Build Diary

The following work will be completed over the next fortnight:

Week commencing Monday 8 May

  • Continuation of substation works
  • Bulk excavation to east and west basement continues
  • Trimming of piles continues
  • Pile cap construction continues
  • Continuation of storm water and sewer pipe and pit installation into existing oncourse systems

Week commencing Monday 15 May

  • Trimming of piles and pile cap construction continues
  • Continuation of bulk excavation to east and west basement  
  • Electrical civil works and substation works continue
  • Continuation of storm water and sewer pipe and pit installation into existing oncourse systems
Club Stand build timeline

The video below is an artist's impression of the new Club Stand, reflecting the projected build progress and timing.