The following work will be completed over the next fortnight:

Week commencing Monday 10 April

  • Trimming of piles continues
  • Pile cap construction
  • Bulk excavation to west basement commences
  • Continuation of storm water and sewer pipe and pit installation into existing oncourse systems
  • Electrical civil works
  • Work ceases Thursday 13th April for Easter

Week commencing Monday 17 April

  • Work resumes Thursday 20 April following Easter
  • Pile cap construction
  • Bulk excavation continuation
Club Stand build timeline