Club Stand Build Diary

The following work will be completed over the next fortnight:  

Week commencing Monday 27 March 

  • Installation of all 543 piles complete including trimming of piles 
  • Commencement of pile cap works 
  • Storm water and sewer works continue with the installation of pipes and pits to carry this into existing on course systems  

Week commencing Monday 3 April 

  • Continuation of pile cap works 
  • Bulk excavation for tunnel 
  • Continuation of storm water and sewer pipe and pit installation 
  • Substation works to commence
Club Stand build timeline
The video below is an artist's impression of the new Club Stand, reflecting the projected build progress and timing.