Club Stand Build Diary

The following work will be completed over the next fortnight:

Week commencing Monday 13 March
  • Continuation of piling installation. 
  • Commence trimming of piles and detailed excavation. 
  • Continuation of installation of storm water pipes and pits.

Week commencing Monday 20 March
  • Continuation of piling installation.
  • Commence trimming of piles and detailed excavation. 
  • Continuation of installation of storm water pipes and pits. 
  • Remove excavated material from site.
Club Stand build timeline