Club Stand Build Diary August

Crane towers over Flemington

Club Stand Build Diary

The tower crane installation for the construction of the Club Stand is now complete, while the in ground service installation continues. The basement tunnel is nearing completion, with the final precast concrete walls expected in the coming week. The second section of ground slab was poured last Friday near the area which will be known as the Courtyard Bar, which will really emphasise the curvilinear shape of the building.

The following works will be completed over the next fortnight:

Week commencing Monday 31 July

  • Strip formwork – Ground Slab pour two
  • Preparation of ground floor pour three and ground beams
  • Preparation of Owners & Trainers slab
  • Services installation (hydraulic and electrical)
  • Generator slab installation

Week commencing Monday 7 August

  • Stair installation for the Substation
  • Pour third ground slab and prepare ground beams
  • In-ground services installation for slab four

Club Stand Build Diary